Purchase
order
Collaborative
construction terms
Guide
to use
Guide to risk
management
Help
Purchase/
Download
About
this project
Feedback
Home
1
Working together
2
Primary obligations of the purchaser
3
Primary obligations of the supplier
4
Risk allocation
5
Performance management
6
Payment
7
General terms
8
Legal definitions

4

Collaborative construction terms

Risk allocation

 

Risk Register

4.1

Risk assessment

Where it is provided in the Purchase Order that the Supplier is responsible for the preparation of the Risk Register, the Supplier will be responsible for carrying out (with assistance from any relevant members of the Supply Chain and any other Project Participants) an initial risk assessment to identify: -

  • potential risks relating to the performance of the Services and/or the delivery of the Project the occurrence of which are capable of adversely affecting the time for completion, cost or quality of the Project;

  • the probability of these risks occurring;

  • a financial estimate of the most likely consequences of each risk occurring (the "risk allowance"); and

  • those risks that are within the control of, or are best managed by, the Purchaser, the Supplier or another Project Participant.

The results of this risk assessment will be set out in the Risk Register.

Where the Supplier is not responsible for the preparation of the Risk Register, the Supplier will nevertheless provide all reasonable assistance in this process where it considers it may have relevant input and/or is requested to provide assistance.

4.2

Updating the Risk Register

Where it is provided in the Purchase Order that the Supplier is responsible for the updating and amendment of the Risk Register, it will carry out these tasks, (seeking the assistance of other Project Participants as considered appropriate) and will arrange regular meetings with the Client and other Project Participants to review and update the Risk Register and to consider:-

  • any new risks that have arisen since the date of the last review;

  • the steps taken to prevent/mitigate previously identified risks;

  • risks which have been successfully prevented/mitigated (which can be removed from the Risk Register); and

  • the prioritisation of all continuing risks and agreement of an action plan in respect of, and risk owners for, all risks prioritised as serious risks.

Where the Supplier is not responsible for the preparation, updating and amendment of the Risk Register, the Supplier will nevertheless provide all reasonable assistance in this process where it considers it may have relevant input and/or is requested to provide assistance.

 

Risk allocation schedule

4.3

The Risk Allocation Schedule

Before the date of the Purchase Order, the Supplier and the Purchaser will have completed the form of Risk Allocation Schedule referred to in the Purchase Order to agree and set out: -

  • the allocation (as between the Purchaser and the Supplier) of any cost and time consequences of each risk referred to in the Risk Allocation Schedule; and

  • the amount (if any) for which the Supplier will be responsible which is also included in the Supplier’s Target Cost or Contract Sum (as the case may be) to deal with the occurrence of each individual risk and the allocation of any costs in excess of this amount; and

  • the period of time (if any) resulting from the occurrence of each risk that the Supplier will accept as being its responsibility and the allocation of responsibility for any time consequences in excess of this period.

The Purchaser’s liability to contribute to the cost consequences of, or grant any extension of time in respect of, any risk shown in the Risk Allocation Schedule will only apply after the amount (if any) shown in the Risk Allocation Schedule as having been included in the Supplier’s Target Cost or Contract Sum has been spent in full. The Purchaser shall not be required to consider any extension of time to the Date or Dates for Completion in respect of any risk shown in the Risk Allocation Schedule unless any time period shown in the Risk Allocation Schedule as being the Supplier’s responsibility has expired. Subject to these conditions, the cost and time consequences of the occurrence of any risk in excess of the amount or time period that are the responsibility of the Supplier will be apportioned in accordance with the allocation set out in the Risk Allocation Schedule.

The Risk Allocation Schedule shall remain fixed throughout the period of the Contract unless both parties agree otherwise and record the agreed changes in writing.

4.4

Notification of the occurrence of risks identified in the Risk Allocation Schedule

If a risk identified in the Risk Allocation Schedule occurs, whoever of the Purchaser or Supplier first becomes aware of the occurrence of the relevant risk will immediately notify the other and both will co-operate to agree the best means of dealing with any adverse consequences of the occurrence of the risk and to mitigate its effects, whether or not the occurrence of the risk also constitutes a Relief Event.

 

Relief events

4.5

Relief Events

The following are Relief Events:-

  • any instruction issued by the Purchaser to change the Services or the Project; or

  • any act, omission or default of the Purchaser; or

  • the occurrence of any risk referred to in the Risk Allocation Schedule to the extent that the Risk Allocation Schedule does not apportion responsibility for the consequences of the risk to the Supplier (provided that the Supplier shall only be entitled to recover additional costs if the cost consequences of the occurrence of the risk exceed the amount (if any) shown in the Risk Allocation Schedule as having been included in the Supplier’s Target Cost or Contract Sum and provided that the Supplier shall only be entitled to seek an extension of time to the Date or Dates for Completion if the time consequences of the occurrence of the risk exceed the period (if any) shown in the Risk Allocation Schedule as being the Supplier’s responsibility); or

  • the occurrence of any risk which is not referred to in the Risk Allocation Schedule and which is not reasonably foreseeable and is beyond the control of the Supplier (excluding any act, omission, default or insolvency of the Supplier, any member of the Supply Chain or any subcontractor of the Supplier) to the extent set out in the Purchase Order;

that has, or is likely to have, any effect on the cost of performing the Services and/or the Date or Dates for Completion.

4.6

Notification of Relief Events

If a Relief Event occurs, or is likely to occur, whichever of the Purchaser or the Supplier becomes aware of it will immediately notify the other of its occurrence or likely occurrence, and both will co-operate in agreeing the best means of dealing with any adverse consequences resulting from its occurrence and in mitigating their effect.

4.7

Involvement of the Project Team

Where either the Purchaser or the Supplier is a member of the Project Team and considers that any Relief Event notified under clause 4.6 may affect any other Project Participant, that party will:

  • promptly inform the Project Team of the relevant Relief Event; and

  • make available to the Project Team any information received in accordance with clauses 4.6 and 4.8

so that the Project Team has an opportunity of considering the Relief Event and its potential impact on other Project Participants. The Purchaser and the Supplier will give serious consideration to any recommendation of the Project Team in relation to the Relief Event.

4.8

Provision of a statement of the likely effect of a Relief Event

As soon as reasonably practicable, and in any event not later than 14 days after notification in accordance with clause 4.6 (or within any other period that the parties may agree) the Supplier will provide a statement setting out (in as much detail as is reasonably practicable) the effect that the Supplier considers the Relief Event will have on the cost of performing the Services and/or the Date or Dates for Completion.

4.9

Provision of further information

The Supplier will provide any additional information and/or explanation reasonably requested by the Purchaser in support of any statement given under clause 4.8.

4.10

Agreement of the effect of a Relief Event

The Purchaser and the Supplier will use reasonable endeavours to agree the effect of any Relief Event referred to in the Supplier’s statement under clause 4.8 and will co-operate to agree any action that reduces or minimises any adverse effect of the Relief Event. If considered appropriate by either the Purchaser or the Supplier, they will meet to discuss any differences between them. Any failure to reach agreement will be resolved in accordance with the Dispute Resolution Procedure.

4.11

Effects of Relief Event too uncertain

If the Purchaser decides that the effect of any Relief Event is too uncertain to be forecast with reasonable accuracy, it will agree with the Supplier the assumptions to be made to enable an estimate of the effect of the Relief Event to be made. If these assumptions subsequently prove to have been wrong, the Purchaser and the Supplier will agree the corrections needed to be made to the original estimate. Any failure to reach agreement will be resolved in accordance with the Dispute Resolution Procedure.

4.12

Purchaser's assessment of the effect of Relief Events in the absence of notification

If the Supplier fails to notify the Purchaser in accordance with clause 4.6 or fails to provide a statement in accordance with clause 4.8, the Purchaser may nevertheless carry out its own assessment of the effect of any Relief Event and will notify the Supplier accordingly. The Purchaser and the Supplier will use reasonable endeavours to agree the effect of the relevant Relief Event and, if considered appropriate by either party, will meet to discuss any differences between them. Any failure to reach agreement will be resolved in accordance with the Dispute Resolution Procedure and the provisions of clause 4.13 will apply in relation to the assessment of the effect of the Relief Event.

4.13

Delay in notification of any Relief Event

In considering the effect of any Relief Event which the Purchaser was not aware of, the parties will take into account any delay on the part of the Supplier in notifying the occurrence of a Relief Event after the date it became aware, or should reasonably have become aware, of the relevant Relief Event and any additional effect of delay (in terms of additional cost or greater disruption of the Services) will be ignored.

4.14

Where the Supplier is a subcontractor

Where the Supplier is a subcontractor, the Supplier acknowledges that, to the extent that the effects of a Relief Event are determined under the Purchaser’s Contract, that determination will be binding on the Supplier, (unless, and to the extent that, the Relief Event is attributable to the fault of the Purchaser, in which case the Purchaser will agree the amount of any additional cost suffered by the Supplier and may either grant an extension of time or require the Supplier to accelerate the Services at the Purchaser’s expense). Any failure to reach agreement will be resolved in accordance with the Dispute Resolution Procedure and the provisions of clause 4.13 will apply in relation to the assessment of the effect of the Relief Event.

 

next...

top...

Be
PO Box 2874
London Road
Reading RG1 5UQ
www.constructingexcellence.org.uk
T 0870 922 0034
F (0118) 975 0404
Email bemail@constructingexcellence.org.uk
Site architecture, publications consultancy, web design and CD-ROM version by Format Information Design