Purchase
order
Collaborative
construction terms
Guide
to use
Guide to risk
management
Help
Purchase/
Download
About
this project
Feedback
Home
1
Aim and
guiding principles
2
Underpinning
collaborative behaviour
3
Flexibility
4
Clarity
5
Other features
6
Informal
definitions
A
Appendix: Draft risk allocation schedule

6

Guide to use

Informal definitions

 

Please note that these are informal definitions designed to give a general sense of key terms and aid understanding of the contract. They are not legal definitions.

For the robust legal definitions that underpin legal interpretation of the contract, please refer to section 8 of the Terms and Conditions.

Client's Brief

See Purchaser's Brief.

Collateral Warranty

A warranty (guarantee) made in parallel to the main contract, rather than as an integral part of it, for example an undertaking that subcontractors will be paid by the Purchaser for work they have done if the Lead Supplier cannot do so.

The term 'collateral contract' is used with the same sense.

Contract Sum

An agreed lump sum to be paid for the whole of the Services, usually in instalments according to a Payment Schedule.

Defects liability period

The period following completion of the project during which the Supplier will be liable for defects in their work and obliged to compensate the Client for them.

Dispute Resolution Procedure

A formal route, explicitly agreed between both parties, through which any disputes that arise during the project will be resolved.

The procedure used in CC projects is set out in section 7 of the Terms and Conditions.

Guaranteed Maximum Cost

An agreed cost for the provision of the whole of the Services, excluding the Supplier's Margin, that cannot be exceeded (except by payments in respect of Relief Events).

Key Performance Indicators (KPIs)

In this context, performance measures that reflect critical or central aspects of the project: the achievement of defined milestones or success overall.

Lead Designer

Designer responsible for all design carried out by others.

Lead Supplier

Supplier responsible for all construction carried out by others.

Liquidated damages

An amount of money, agreed upon by both parties, that one will pay to the other in specified circumstances, such as (for example) a delay in the completion of the project.

Milestone

A key event or specific achievement during the life of the project.

Open book accounting

An arrangement where both sides agree to let the other inspect their accounts, perhaps including information on budgets available and profit that has been made.

Often a key aspect of collaborative or partnering arrangements.

Overriding Principle

The overriding principle of CC projects is collaboration: working together in a co-operative and collaborative manner in good faith and in the spirit of mutual trust and respect.

Payment Schedule

A document setting out when part-payments of a Contract Sum will be made, perhaps linked to when activities are completed or milestones reached.

Performance measures

Ways of assessing whether (or how well) the contract has been fulfilled and the project delivered.

The terms 'performance metrics' and 'performance indicators' are also used in this sense.

Products

Physical commodities to be delivered under a contract, as opposed to services to be performed.

Project Programme

A document setting out the sequence of events (components, milestones, schedules) and responsibilities of the project.

Project Protocol

A document setting out the joint aspirations of the Project Team with regard to the project, as well as how they will work together to achieve them.

The Project Protocol expresses intentions over and above contractual obligations with regard to working together. It is signed by all members of the Project Team.

The term 'partnering charter' is also used with this sense.

Project Team

A team set up for each Project, comprising the Client and other participants considered by the Client to be of key importance to successful project delivery.

Purchaser's Brief

A document produced by the Purchaser and attached to the Purchase Order (at Appendix 1) that sets out what is required from the Supplier.

Also known as the Client's Brief.

Purchaser's representative

An individual appointed by the Purchaser who acts on their behalf and is the first point of contact for the Supplier.

Relationship

The less formal dimension of an agreement or working arrangement, including:

  • attitudes and behaviours (as opposed to defined procedures)

  • verbal, as opposed to written, communication

  • the way the parties regard each other (as opposed to how they are legally or explicitly defined)

  • the spirit in which problems are faced.

Relief Event

Any event that has an effect on the cost of performing the Services, or the date of their completion, including the occurrence of risks both foreseen and unforeseen.

Risk

A possible outcome that could endanger part or all of the project if it occurred.

Risk Allocation Schedule

A document setting out the contractual allocation of risks between the Purchaser and the Supplier.

Risk allowance

The total estimated financial effect of a risk occurring.

Risk Register

A document listing all the risks identified on a project, the likelihood that they will arise, who 'owns' them, and the actions that are being taken to minimise them or that will be taken if they arise.

Services

In this document, this term is intended to cover works and/or services in the traditional sense.

Supplier's margin

An agreed amount or percentage paid to the Supplier to cover profit, central office and site overheads and so on (as opposed to their actual costs on the project).

Supply chain

Collective term to describe a group of companies whose various individual goods and/or services combine in the delivery of a project, service or product.

This can be through subcontracting arrangements, teamworking, or straightforward purchasing.

Target Cost

An amount agreed in respect of the Supplier's profit and overheads that is paid to them in instalments during the contract period.

top...

Be
PO Box 2874
London Road
Reading RG1 5UQ
www.constructingexcellence.org.uk
T 0870 922 0034
F (0118) 975 0404
Email bemail@constructingexcellence.org.uk
Site architecture, publications consultancy, web design and CD-ROM version by Format Information Design